WORKED EXAMPLE
How to cost a job before preparing a quotation
| Step / input | Worked example |
|---|---|
| Materials | R1,600 |
| Labour | 2 painters × 8 hours × 2 days × R75 = R2,400 |
| Equipment, sundries and transport | R400 + R105 + R250 = R755 |
| Direct cost | R4,755 |
| With R300 overhead and 5% contingency | (R4,755 + R300) × 1.05 = R5,307.75 |
| With 25% markup | R6,634.69 before any tax |
| For 120 m² output | R55.29 per m² |
Check before using the result
A selling rate is only as complete as the estimate. Avoid counting salary on-costs, fuel or equipment costs twice. Whole-pack charging and consumed-material costing answer different questions. No VAT, statutory wage calculation or automatic assessment of exclusions is performed.
Read the full itemised job costing & pricing guide →Technical references & scope
Method reviewed 4 November 2026. Planning estimates; input rates and assumptions require project review. References support the method and do not certify this tool.
Each material line can charge whole packs or only the quantity consumed. Include all costs once; no tax is added automatically.