Maintenance · FREE PLANNING TOOL
Machine service planner
Plan named service tasks from meter readings and calendar deadlines, with working days and exclusions.
Need help with the inputs? How to calculate a machine’s next service date · See a worked example
WORKED EXAMPLE
How to calculate a machine’s next service date
| Step / input | Worked example |
|---|---|
| Current meter | 1,250 operating hours |
| Next meter service | 1,500 operating hours |
| Hours remaining | 250 |
| Daily use | 14 hours → 17.86 equivalent operating days |
| Service falls during | Operating day 18 |
| Mon–Fri from 4 November 2026 | 27 November 2026, without excluded dates |
| If calendar deadline is 20 November | 20 November controls instead |
Check before using the result
The forecast does not approve the interval or reset an overdue task. For an already-due meter task, the forecast start is an immediate-attention date, not its reconstructed historical due date. Downtime may overlap between tasks and should not automatically be summed.
Read the full machine service planner guide →Method, assumptions & scope
Remaining hours = next due meter − current meter. Hour-trigger day = ceiling(remaining hours ÷ daily meter hours), mapped to operating dates. For a combined trigger, select the earlier of meter forecast date and calendar deadline.
Meter reading is taken before any operation on the forecast start date. Calendar deadlines remain deadlines even on non-operating days. Forecast hours are added only on selected operating dates.
Hour and calendar triggers use the earlier deadline. Read the machine-specific schedule: initial services, conditions and tasks may differ. The tool does not reset overdue tasks or send reminders. For already-due meter tasks, the forecast start is an immediate-attention date, not an inferred historical due date. Forecast is capped at 100 years.
Service tasks may overlap. Labour and costs are summed; downtime is shown per task and is not automatically added across simultaneous work.
Example quantities and rates are illustrative. Replace them with measurements, product data and current supplier rates for your project. A zero price means no price has been supplied.
Technical references
Method reviewed 4 November 2026. References support the approach; manufacturers have not approved or endorsed this calculator.