Construction · FREE PLANNING TOOL

Concrete volume & supply planning

Measure concrete elements and choose ready-mix, complete premix bags or a specified site-mix material schedule.

WORKED EXAMPLE

How to calculate concrete volume and material quantities

Step / inputWorked example
Slab volume5 m × 5 m × 0.1 m = 2.5 m³
With 5% allowance2.5 × 1.05 = 2.625 m³
Ready-mix at 0.1 m³ incrementsRound order to 2.7 m³
Complete premix at a declared 17 L/bag2,625 ÷ 17 → 155 complete bags
Illustrative specified cement schedule400 kg/m³ × 2.625 m³ = 1,050 kg → 21 × 50 kg cement-only bags

Check before using the result

The example cement schedule is arithmetic, not a recommended structural mix. Strength, water content, aggregate properties and application requirements cannot be established from volume alone. Reinforcing, formwork, subbase, water and admixtures are outside this tool’s material total.

Read the full concrete volume & supply planning guide →

Method, assumptions & scope

Rectangle volume = length × width × depth. Cylinder volume = π × diameter² ÷ 4 × height. Multiply each by count and add allowance. Apply the selected supply yield or material schedule.

Complete premix bags contain cement and aggregates. Their mixed yield is product-specific; 17 litres is an illustrative yield documented for one 36.2 kg product, not a universal bag value.

Site-mix mode requires your specified materials per wet m³; it does not infer strength from a ratio. Water, admixtures, reinforcement, formwork and subbase are excluded. Supply rates do not certify structural suitability.

Example quantities and rates are illustrative. Replace them with measurements, product data and current supplier rates for your project. A zero price means no price has been supplied.

Technical references

Method reviewed 4 November 2026. References support the approach; manufacturers have not approved or endorsed this calculator.